Industry News:
Gunite
Cleaning and Restoration
Concrete Repair
Protective Mortars & Coatings
Brickwork Repair
Sprayed Concrete
Car Park Refurbishment
Structural Strengthening
Roofing & Deck Membranes
Waterproofing
Internal and External Wall Insulation
Corrosion Protection
Heritage Building Restoration
Partnering
Gunfire
Fire Doors
Fire Safety Compliance
Fire Stopping & Boarding
Intumescent Coatings
Fire Retardant Coatings
Acoustic & Air Sealing
Testing
Create
Bespoke Joinery
CAD
Commercial Fit-Out
Education Fit-Out
Heritage Fit-Out
Office Refurbishment
Residential Fit-Out

Case Studies

Case Studies
Project       Intumescent Paint and Fire Stopping at St Georges Tower by Gunfire
Main Contractor       Pettifer Construction
Duration       60 Weeks
Value       £650,000

Intumescent paint application and fire stopping works at St Georges Tower, Leicester, carried out by Gunfire.

 

Scope of Works:

  • 90 minute fire protection to steelwork using intumescent paint
  • Boarded insulation to internal/external soffits
  • 11 floors of fire stopping to service riser floors and wall penetrations
  • 90 minute fire protection to steelwork using boarded system