PROBLEM AND SOLUTION
Contracted by the University of Birmingham, we were engaged to carry concrete condition testing and subsequent concrete repairs and the application of protective coatings.
Hammer, carbonation and chloride tests were carried out on the concrete followed by concrete repairs to the window cills, columns and panels and stairwells and staircases. A migratory corrosion inhibitor was also applied overall.
OUTCOME
All areas of the newly repaired building were protected through the application of an anti-carbonation coating with a clear (non-pigmented) coating applied to the pre-cast, exposed aggregate concrete panels. Other works included localised brickwork repairs and re-pointing; flat roof repairs to projecting bay roofs including enlarging existing rainwater outlets and liquid-applied coatings to stairwell roofs. The 15-year Sika warranty for the concrete repairs and coatings was issued on completion.