Projects
IBIS Hotel London
PROJECT HIGHLIGHTS
The façade of the 12-storey IBIS Hotel has dominated the west-London skyline of Earl’s Court since its original construction in the 1970’s. Its distinctive exterior consisting of pre-cast reinforced concrete exposed aggregate panels required a full exterior clean prior to a programme of concrete repairs and the application of protective anti-carbonation coatings.
PROBLEM AND SOLUTION
Accessing the entire exterior of the building via a combination of fixed scaffolding and cradles, the building was cleaned by water jetting to remove surface contaminants and debris.
Once cleaned, a full hammer tap survey was carried out to identify areas requiring concrete repairs.
OUTCOME
Sika’s Ferrogard®-903 migratory corrosion inhibitor was then spray applied to all external surface areas totalling some 8,500m2. MonoTop®-3020 – a cementitious surface-finishing mortar – was then applied overall as a pore-filler prior to the application of the anti-carbonation coatings. This ensured a blowhole-free surface for correct technical performance of the subsequently applied Sikagard®-5500 elastomeric & protective coating.