PROJECT HIGHLIGHTS
This project comprised the complete repair and part reconstruction of the badly damaged retained reinforced concrete façade of the old Nestle factory in Hayes, Middlesex, an historically important industrial structure. The re development of the site incorporated retaining the façade of the original Nestle factory as its main front elevation.
PROBLEM AND SOLUTION
The retained façade of the old factory had to be fully repaired and protected, having exhibited a broad range of issues.
Low cover to reinforcing steel, loss of section due to reinforcement
corrosion, deeply carbonated concrete, cracking as a result of both movement and reinforcement corrosion and multiple layers of protective – but damaged & flaking – coatings. All remedial works also had to carry a minimum of a 20 year warranty.
OUTCOME
Once grit-blasted to remove all existing coatings, significant repairs were carried out using Sika Monotop structural repair mortars, Sika’s Ferrogard 903 migratory corrosion inhibitor and Sika Monotop – a 5mm surface levelling mortar, important for re-profiling all column & beam edges to reinstate to original profile and to mask repair areas. Sikagard anti-carbonation coatings were then applied to all surfaces (c. 1500m2)